Mail # 70113 Part 1 : SB_GT&S_0768535.pdf

» Back Back...

Date:
Friday, 12 September 2014 13:37
Sender:
Chen, Jun M. (jun.chen@cpuc.ca.gov)
Recipient:
Confidential Material Removed; Jacobson, Erik B (RegRel) (/O=PG&E/OU=Corporate/cn=Recipients/cn=EBJ1); Tran, Lana (lana.tran@cpuc.ca.gov); Tse, Rick (rick.tse@cpuc.ca.gov)
Subject:
RE: Diablo diesel information
Total file(s): 2

SB_GT&S_0768535.pdf
SB_GT&S_0768537.pdf
Content:

---------------------Page 1---------------------
From: Chen, Jun M.
Sent: 9/12/2014 1:37:57 PM
Redacted
To:
Cc: Jacobson, Erik B (RegRel) (/Q=PG&E/OU=Corr)orate/cn=Recipients/cn=EB.Jl);
Tse. Rick (rick.tse@ctmc.ca.gov): Redacted
Redacted Tran, Lana
(lana.tran@cpuc.ca.gov)
Bee:
Subject: RE: Diablo diesel information
Hi Lisa,
Please see the attached documents request for the DCPP Unit 2 capscrew incident. Email
submittal is preferred.
Sincerely,
Jon
FromjRedacted
Sent: Friday, August 29, 2014 9:53 AM
To: Chen, Jun M.
Redacted
Cc: Jacobson, Erik B (RegRel)' i
Subject: RE: Diablo diesei information
Hello Jon,
Following up on your earlier email and voicemail. Yes, DCPP Unit 2 is back online. The
station has initiated two root cause evaluations, one on the hardware problem, and a second on
the organizational performance, it will most likely be a couple weeks before either of the root
cause evaluations are complete.
I will keep you posted as I know more.
SB GT&S 0768535
---------------------Page 2---------------------
Kind Regards,
Redacted
iS Before printing this email or any attachments, please think about your responsibility and commitment to the ENVIRONMENT.
SB GT&S 0768536